Project :
|
The Revolution Leaders Museum
|
 |
Client:
|
Salah Emam Contracting Co.
|
Consultant:
|
Mustafa Hamed Consulting Office
|
Location
|
Cairo
|
Budget:
|
Approximately 3,000,000 LE
|
Duration:
|
From January 2004 till July 2004
|
Type Of Works:
|
Diaphragm walls, horizontal grout blanket, Piling works and
Dewatering.
|
Project Description:
|
One of
the major challenging
projects in Egypt nowadays,
The project required to
install additional
foundation elements within
the interior perimeter of
an already existing
building. Bauer Egypt
managed to mobilize a BC-15
to install the perimeter
100cm thick diaphragm walls,
a BG-11 to install the
80&120cm diameters piles and
a BG-7 to install grouting
points of the horizontal
grout blanket.
|