Experience Record For Post Grouted Bored Piles                         Print Friendly
Year Project Name Location
(Egypt)
Client Consultant /
Architect /
Engineer
Project Duration (Months) Piles dia. (mm) Total No. Of Piles Pile length (m) Soil Condition Remarks 
1981 Baher Tower Cairo Society. of Diplomats Consulting Group 8 1200 74 24 Clay/Sand  
1981 Nile Center Cairo Malaco Alimar Int. Dr.Ali AbdulRahman 4 1200-980 140 19 Clay/Sand  
1981 Sky Tower Cairo Malaco Alimar Int. Dr.Ali AbdulRahman 6 1200 70 18 Clay/Sand  
1982 Agouza Medical Center Cairo Kassel Turkey System ACE 6 980-780 52 13 Clay/Sand  
1982 Barclays Bak Cairo C.R.C. - Hassan Dorrah Co. Ove-Arup 3 980-780 92 19 Clay/Sand  
1982 Information & Research Center Cairo El-Nasr Company - EGYCO - Research Center 2 980-780 52 20 Clay/Sand  
1982 Bank Of Kuwait Alexandria Alex. International Housing Co., Dr.G.Bakry 2 1500-1200 29 20 Clay/Sand  
1982 Menouf Substation Menouf Simens / Egypt Electric A.U.C   5 520 172 18 Clay/Sand  
1982 Merryland res. Building Cairo Puplic Housin & Reconstruction Co. Dr. Ali Sabry 5 1500-1200 128 18 Clay/Sand  
1982 Misr Bank Cairo Allam/Cemmentation    7 1500-1200 100 26 Clay/Sand  
1982 Roushdy Center Alexandria Malaco Alimar International Dr.Ali AbdulRahman 8 980 212 15 Clay/Sand  
1983 Agricultural Tower Alexandria Mediterranean Sea Company   3 980-780 218 10 Clay/Sand  
1983 American Embassy - Cairo Cairo U.S.A State Dep. - Kramico F.B.O 5 980-780 283 18.5 Clay/Sand  
1983 Faisal Bank Cairo Faisal Bank Dr.Hewedy 3 780-650 97 16 Clay/Sand  
1983 Maadi Center Maadi Malaco Alimar International Dr.Ali AbdulRahman 4 1200-980 167 18.5 Clay/Sand  
1983 Pharma Building Hoechst. Cairo Hoechst A.G.   1 780 36 16 Clay/Sand  
1984 Abu-Sumbol Tower Cairo Abu Sumbol Company Architect Group 7 1200-980 92 17 Clay/Sand  
1984 Alia Tower Cairo Mediterranean Sea Company ASA 2 980-780 119 15 Clay/Sand  
1984 Gezira Tower Cairo Degla for Eng. & Const. Co.   4 980-780 69 15 Clay/Sand  
1984 Lawyers Tower Cairo C.R.C. - Hassan Dorrah Co. Dr.Ali AbdulRahman 3 1200-980 118 18 Clay/Sand  
1984 Shoubra Res. Building Cairo Saudi Egyptian Co. SEPCO   2 980-650 198 17 Clay/Sand  
1984 Sphinx Tower Cairo Dr. Ali Raafat   2 980-650 111 19 Clay/Sand  
1984 State Council Building Cairo Puplic Housin & Reconstruction Co.   10 1200-980 252 19 Clay/Sand  
1984 Air Port Bridge Cairo Arab Contractors ACE 2 1200-980 106 25 Clay/Sand
1985 Agha Khan res. building Cairo C.R.C. - Hassan Dorrah Co. Dr.Hewedy 12 1200-1000 1105 20 Clay/Sand  
1985 Etap Tower Cairo Inter. Contr. Co.   2 1200-980 39 20 Clay/Sand  
1985 Gawharet El-Nile Cairo Misr Reconstruction Co. ACE 8 1200-1000 946 15 Clay/Sand
1985 White Home Cairo Ramada Company Dr.Ali AbdulRahman 1 980,780 82 19.5 Clay/Sand  
1986 El-Mona Tower Cairo Dr. M. El-Rifai Dr.M.Dorra 1 1200-980 51 20 Clay/Sand  
1986 Maadi Complex Maadi Eng. H. Abo-Elfotoh ASA 5 1200-980 242 19 Clay/Sand  
1986 Al-Hoda Tower Maadi El-Hoda Misr Dr.M.Dorra 3 1200-980 169 19 Clay/Sand  
1987 Al-Haramien Tower Cairo El-Ghannam Co. Dr.S.AbdlelSalam 1 1200-980 63 24 Clay/Sand  
1987 El-Hegaz Tower I Giza Arab Engineering For Construction Dr.S.El-Khoraiby 1 980-780 35 23 Clay/Sand  
1987 El-Hegaz Tower II Cairo Eng. Ashraf Ismaail   1 1200-980 43 16 Clay/Sand  
1987 Zamalek Complex Cairo Interexport Company Sabboor 5 980-780 130 17 Clay/Sand
1987 El-Boustan Car-Park Cairo C.R.C. - Hassan Dorrah Co. E.C.G 3 780-650 326 19 Clay/Sand  
1988 Ramadan Fighters Union Cairo Ramadan Owners Union Dr.El-Essely 5 1200-980 377 16.5 Clay/Sand  
1988 Swiss Tower Cairo P IT C O Dr.H.Elemam 6 980-820 344 26 Clay/Sand  
1988 Admin. House. Building Cairo Mr. A. Fouad   1.5 870-980 52 17.5 Clay/Sand  
1988 Cairo Medical Center Cairo Cairo Medical Union Degla Co. 2 870-650 119 17.5 Clay/Sand  
1988 Abu-Qir Power Plant Alexandria S O G E A EEA 6 800-650 748 21.5 Clay/Sand  
1988 El-Zahraa Tower Cairo S E C O N SECON 1.5 980-780 41 14 Clay/Sand  
1988 El-Nile Building Cairo Degla Company   1 980 32 23 Clay/Sand  
1988 Makkah Tower Cairo Arab Eng. for Roads & Brid.   2 800-650 93 16 Clay/Sand  
1989 El-Sharabia Center Cairo Central Nile Co. for Roads & Bridges Beltic  1.5 650 67 27 Clay/Sand  
1989 El-Khaldia Tower Cairo Khalidia Cont. Co.   2.5 980-780 90 13 Clay/Sand  
1989 Al-Shaboura Bridge Ring Road Misr Concrete Co. ACE 2.5 800 127 18 Clay/Sand  
1989 Zahret Mosadak Cairo Eng. Sami Rizk   1 980-780 60 16 Clay/Sand
1989 Tanta Complex Tanta Misr Insurance Co.   4 980-800 472 21 Clay/Sand  
1989 El-Ramad Hospital Cairo Arab Contractors Arabco 2.5 650 195 17 Clay/Sand  
1989 Faisal Tower Giza El-Gezera for Investments Dr.Ali AbdulRahman 10 1200-1000 190 20 Clay/Sand  
1989 El-Watania Tower Cairo C.R.C. - Hassan Dorrah Co.   2 800-1000 110 14 Clay/Sand
1990 Al-Ahram Newspaper Building Cairo The Egypt. Eng. & Trade. Co. Sabboor 2 1000-800 84 23 Clay/Sand  
1990 Indoor Sports Hall Cairo Arab Contractors Dar Elhandasa  2.5 1200-1000 420 20 Clay/Sand  
1990 Gezeret El-Maadi Tower Maadi El-Nile for ReconstructionCo. Dar Elhandasa  6.5 1000-800 236 15 Clay/Sand  
1990 Al-Esraa Tower Cairo C.R.C. - Hassan Dorrah Co. Dr.M.Dorra 1 1000-800 66 15 Clay/Sand  
1990 El-Maryoutia Bridge Giza Mosahmet El-Behera Co. ACE 3 800-650 184 16 Clay/Sand  
1990 Soultan El-Bahary Bridge Ring Road Mosahmet El-Behera Co. ACE 1.5 650 163 15 Clay/Sand  
1990 Al-Tayseer Tower Cairo Al-Tayseer Owners Union Dr.Abu Zied  5 1000-800 114 15 Clay/Sand  
1991 Bahethat El-Badiah Building Cairo S E C O N SECON  2 800-650 128 14 Clay/Sand  
1991 26 Gameat El-Dewal Str. Build. Mohandseen Eng. El-Sayed A. Mohsen Dr.Sabry 1.5 980-780 69 19.5 Clay/Sand
1991 U.S.Embassy ( II ) Cairo U.S.Embassy F.B.O 2 650 100 16 Clay/Sand  
1991 Horgada Beach Hotel Horgada Med. Sea Contracting Ltd. ASA 3 800 440 11 Clay/Sand  
1992 Syria Tower Giza Essa Company Dr. M. Kafrawy 2 800-1000 70 24 Clay/Sand  
1992 Abu-Shamar Building Giza Eng. Mostafa Abdel-Moeaz Dr.Abu Elid 2.5 800-1000 81 16 Clay/Sand  
1992 First Residential Complex Giza International Bechtel inc. Ove-Arup 7 1000-1200-1500 247 18 Clay/Sand  
1992 Police Housing Maadi Arab Contractors Dr.Dorra 5 800-100 550 16 Clay/Sand  
1993 Assiute silos Assiute Amoun Contractors Dr.H.ElEmam 2.5 800 325 17 Clay/Sand  
1993 El-Sadat Academy Maadi Arab Contractors Dr. A. Raafat   800-1000 106 12 sand  
1993 Al-Tannora School Cairo Kwait. Arab. Fund. for Econ. Dev. ACE 1 800 88 18 Clay/Sand
1993 Mosadak Tower Giza Arab Contractors ACE 1 800 40 17 Clay/Sand  
1994 Saray El-Maadi Tower Maadi Sadco Eng. & Contract. Dr.A.Subry 2 1000-1200 42 16 V.D.sand  
1994 Zagazig Grain Silos Zagazig Amoun Contractors Dr.H.ElEmam 3 800 320 17 Clay/Sand
1994 El-Haramien Tower Maadi El-Ghanem Contractors Dr.S.AbdelSalam 2 1000-1200 60 16 Clay/Sand  
1994 EEA Ware House Nasr City E.E.A. Hamza Associates 4 600-800 110 16 Clay/Sand
1994 Zagazig res. building Zagazig El-Nile for Const. Co.   4 650-800 105 15 Clay/Sand  
1995 Zahret El-Maadi Maadi Saudi Egyptian Company Dr.Abu Elid 3 1080 221 19 Clay/ Sand  
1995 El-Manyal  Resid. Building Cairo El-Khaldia Co. for Contracting Dr.Ali AbdulRahman 2.5 800-1000 170 17 Clay/Sand  
1995 Al-Akhbar Building .. Cairo Arab Contractors Sabour 6 800-1000 900 17 Clay/Sand  
1996 Le-Meridien Hotel  Garden City  International Bechtel Inc. ACE 4 1200-1500 300 20 Clay/Sand
1996 Riad El-Maadi (Tawer 2) Maadi Saudi Egyption Co. Dr.Abu Elid 2 800 148 18 Clay/Sand  
1998 Quatar Embassy   Mohandseen Saudi and  Partners Co. ACE 1.5 650 160 16 Clay/Sand  
1998 AUC academic Center  Cairo  American University in Cairo H2L2 / Wassef 6 800-1000 350 18-22 Clay/Sand  
1998 Nile Plaza Complex  Cairo  Nova Park Co. Hamza Associates 8 800-1000-1200 88&
390
35&
38
Clay/Sand  
1999 Nile City  Cairo  Orascom  Hamza Associates 6 1000-1200 426 36 Clay/Sand  
1999 Abdel Salam Aaraf Bridge El-Mansora El-Nile For Roads & Bridges Co. Hamza Associates 2 1200 820 36 Clay/Sand  
2000 San Stefano Complex  Alexandria San Stefano for Real State Company Hamza Associates 10 1000
1200
1500
700 36 Sand/C.Sand  
2001 Children's Oncology Hospital Cairo Skanska International Hamza Associates 4 1000
1500
200 20 Clay/Sand  
2005 Burj Ul-Behar, Tripoli-Libya Lybia Hashoo Group Limited Meinhardt PTE LTD (Singapore)

5

      1000
       800

    142

21 Sand/Sandstone  
2006 Saudi Embassy Consulate Office Building Giza C.C.C. Buro Happold

6

    650 ,800
    1000,1200

   185

11 - 22 Clay  
2007 Liquid Bulk Terminal Project, Ammonia Tanks, Sokhna Port Sokhna Port OCL KBR

3

      1200
       1500

    93
    72

41.5 Clay  
2007 Kalyoub Bridge Kalyoubia Hasan Allam Company  

2

       600,1000

    190

22 - 28   Clay/Sand  

 