Experience Record For Dewatering Works  Print Friendly
Year Project Name Location (Egypt) Client Consultant /
Architect /
Engineer
Project Duration (Month) Well Dia. (cm) No. of Wells Length Of Well (m) Drawdown of water (m) Area Of Dewatered Pit (m2) Average Pumping Rate (m3/h) Remarks
1981 Abu-Sultan Power Station Ismaailia General Electric General Electric 12 30 30 30 4.5 5000 1000 -
1982 Agoza Medical Center Cairo Kassel Turnkey System ACE 12 30 10 18 3.5 1500 300 -
1983 U.S Embassy - Cairo (1) Cairo kramico Dr. Hewedy 36 30 18 18 3 2000 360 -
1984 Sheraton Extension Cairo Dong San ACE 12 30 20 15 3 1100 320 -
1985 Gawharet Cornish El-Nile Giza Sami Saad Company ACE 6 30 18 17 3.5 3000 500 -
1986 Foustat Water Works Cairo Egyptian Contracting - 4 30 26 20 6 2500 600 -
1986 Contract # (21) Cairo C.W.C. Ambric 0 30 25 20 - - - Installation only
1986 Contract # (22) Cairo C.W.C. Ambric 0 30 25 21 - - - Installation only
1988 Abu Quir Power Plant Alexandria SOGEA Sogea 0 30 8 28 - - - Installation only
1989 Faisal Tower Giza El-Gezira for Investement Dr. Ali Raafat 6 30 15 28 - - - Installation only
1991 U.S. Embassy- Cairo II Cairo EBASSCO F.B.O. 0 30 24 20 4 2000 250 -
1991 Contract # (4) Cairo Arab Contractors Arabco 0 30 100 25 - - - Installation only
1991 Contract # (24-1) Cairo Indust. & Eng. Project Co. Arabco 0 30 30 24 - - - Installation only
1992 First Residential Complex Giza International Bechtel Inc. Ove- Arub 12 30 40 16 4 6000 350 -
1999 Nile Plaza Cairo Nova Park Company Hamza Associates 20 30 22 30 7 7000 400 -
2000 San Stefano Complex Alexandria San Stefano for Real Estate Hamza Associates 20 30 64 35 11.5 28000 5700  
2002 Agriculture Development Bank Giza  Arab Contractors Dr. Ashraf El-Zanaty 6 30   20 7 6000    

2004/
2005

New Naga Hammadi Barrage & Hydropower Plant Naga Hammadi Vinci / Bilfinger Berger / Orascom Joint Venture Lahmeyer International 24 80 50 37/23 25 240000    
2006 Saudi Consulate Giza  C.C.C. Buro Happold 6 80 13 1 1 4500 40  
2006 Sofitel Pump Station Cairo CCC Ehaf. 3 30 2 25 9 40    

 